Construction

Project Name Daemyung 5 Factory - Phase 5
2021/12/23 (After begin construction 50 weeks)

2021/12/11 (After begin construction 48 weeks)

We have stopped construction for few months by Investor's request  due to the Covid Situation

2021/07/16 (After begin construction 26 weeks)


2021/07/03 (After begin construction 24 weeks)


2021/06/21 (After begin construction 23 weeks)


2021/06/05 (After begin construction 20 weeks)


2021/05/20 (After begin construction 17 weeks)


2021/05/05 (After begin construction 15 weeks)


2021/04/17 (After begin construction 12 weeks)


2021/04/03 (After begin construction 10 weeks)


2021/03/20 (After begin construction 8 weeks)


2021/03/06 (After begin construction 6 weeks)


2021/02/20 (After begin construction 4 weeks)


2021/02/03 (After begin construction 3 weeks)


2021/01/23 (After begin construction 2 weeks)


2021/01/12 (After begin construction 1 weeks)




Project Daemyung Chemical Vina Co., Ltd.
Period 2021
Location Long Thanh IP, Dong Nai Province
GFA 6146.92 GFA (m2)
Status Completed